Eversource in New Canaan: Gas Update
Crews from Burns Construction will continue gas construction activities to install and improve our natural gas distribution system in New Canaan according to the following information:
MAIN INSTALLATION
Crew 1 - South Ave & Maple St 7/15 – 7/16, 7 am – 5 pm
Crew 1 - Lakeview & Main St 7/17 – 7/19, 8:30 am – 4 pm
NIGHTWORK
Crew 2 - Park Street to Access Rd 7/14-7/19, 8 pm – 5 am
SERVICE INSTALLATION
Crew 3 - Fieldcrest Road 7/15 – 7/19 , 7 am – 5 pm
Hoyt Street (Darien)
Southwood Drive
Harrison Avenue
What You Can Expect:
Temporary paving activities will be performed in conjunction with our construction activities as needed.
There will be no construction work performed on Saturday.
Construction crews will work daytime and nighttime hours and in-street construction work may vary depending on location.
Access to residences and businesses will be maintained to ensure priority passage of emergency vehicle traffic through construction areas.
Construction activities may take place at multiple sites along the route until the project is complete.
Work zones will be protected from pedestrians and vehicles. Police officers or flagmen will oversee traffic control. Please note that construction work is weather dependent. All construction activities are subject to change without notice.
Click here for further information