Branchville TOD Project Brings Improvements to the Branchville Area

Work near the intersection of Routes 102 and 7 and the Branchville train station will commence during the week of April 24th. This work will bring new sidewalks, lighting, landscaping, and improved access for pedestrians to businesses in the area. 

The following work is scheduled to take place:

  • Tuesday, April 25th: Onsite Services will be installing construction signage starting at 9am and finishing at approximately 3pm 
  • Wednesday, April 26th: Mcllelan Tree Clearing will perform clearing & grubbing starting at 7am and finishing at approximately 3pm 
  • Thursday, April 27th and Friday, April 28th: J. Iapaluccio will perform construction staking
  • Monday, May 1st: Berkshire Concrete Cutting will saw cut roadways starting at 7am and finishing at approximately 3pm 

Continuous updates will be provided to the public in order to keep all informed on the work taking place and any changes to the schedule. 

Thank you for your understanding and support as we work to enhance the Branchville area. 

 *Image courtesy Western CT Council of Gov't Transit Oriented Development Plan