Roads to be Chip Sealed in August
Work expected to be completed within two weeks. Schedule subject to change due to weather and contractor availability.
- Ballantine Park
- Beecher Drive
- Berkshire Road
- Crook Horn Road (Roxbury Road into Settlers Park)
- Housatonic Trail
- Mansion House Road
- Old Poverty Road
- Pascoe Drive
- Short Rock Road
- Sylvan Crest Drive
- Westenhook Terrace
Mill and Pave projects tentatively scheduled for September:
- Cedar Crest Drive
- Georges Hill Road (from just South of Laurelwood Lane to just south of Cooper Hill Road)
- Lakeside Road (Georges Hill Road to Fish Rock Road)
- Parking lots within the town complex (Town Hall lower lot, Fire Dept. upper lot, Police lot)
Road Reconstruction scheduled for September:
- Hickory Lane
Tree Removal in preparation for Road Reconstruction:
- Hollow Swamp Road
Catch Basin Repair as schedule allows:
- Heritage Road (Pomperaug River Bridge to Bates Rock Road)
- East Hill Road (Old Poverty Road to Fairway Drive)
Spot Paving this fall:
- Cedar Trail
- Midland Trail
- Spring Trail
Please note: schedules subject to change due to weather conditions.