State of Connecticut Paving Schedule for Westport Road
The State of Connecticut is planning to mill and pave Westport Road from Route 7 to Chestnut Hill Road.
Hours of Operation will be from approximately 7 pm to approximately 5:30am.
Milling work will begin on or about July 7. This portion of work will take approximately 1 week (all weather permitting).
Paving work will begin on or about July 17th. This portion of work will take approximately 1 week (all weather permitting). The State of Connecticut will have an inspector on-site during this time.
If you have immediate questions during work, please reach out to the State inspector. Or you may call their office at 203-389-3035.